Lesson Learned





No user selected

Report No.

304

Discipline/Origin

Drilling
No origin

Well

Canela
6507/7-16 S

Date created

2019/01/07
2526 days ago

Project Phase

Planning
Project Phase

LL Type/Classification

Time Estimate
Negative

Island Innovator


What happened in Rig move:
DP trial was performed, spent 5 effective hours (+ 3 hours WOW).

What Was Planned

Marine/ Drilling DP trial was not planned/included in Rig Moce Scope nor in AFE.

What Was Learned

DP trial is a requirement from the Island Drilling Management System and is considered good practice when using DP/POSMOOR systems.

What Actions Are Required

Include 5 hours for DP trial in Rig Move Scope and AFE for future operations.